Construction

Progress of the Mountain Valley Pipeline, as of July 23, 2020

Total Miles in Spread (% of total route) Trenched Miles (% of spread finished) Backfilled & Tied-In Miles (% of spread finished) Final Restoration (% of spread finished)

Spread A 34.8 (11.48%) 34.8 (100%) 33.23 (95.5%) 27.21 (78.2%)

Spread B 30.6 (10.09%) 30.6 (100%) 29.25 (95.6) 24.84 (81.2%)

Spread C 33.2 (10.95%) 33.2 (100%) 30.41 (91.6%) 19.35 (58.30%)

Spread D 29.6 (9.76%) 29.6 (100%) 25.39 (85.8%) 17.25 (58.30%)

Spread E 26.3 (8.68%) 26.3 (100%) 24.32 (92.47%) 20.35 (77.40%)

Spread F 40.6 (13.39%) 35.26 (86.86%) 34.80 (85.72%) 30.81 (75.90%)

Spread G (includes Nat'l Fst) 32.2 (10.62%) 6.27 (19.48%) 6.27 (19.48%) 4.06 (12.62%)

Spread H 31.6 (10.42%) 20.07 (63.53%) 15.78 (49.93%) 5.72 (18.10%)

Spread I 44.2 (14.58%) 44.2 (100%) 36.42 (82.40%) 5.97 (13.5%)

Total 303.1 (100%) 260.30 (85.88%) 235.87 (77.82%) 155.56 (51.32%)